Foundation Calculator: Footings, Walls & Slabs

Foundation concrete planner

Estimate your foundation, component by component

Calculate concrete for continuous footings, poured stem walls, and a separate slab. Get a component breakdown, cubic yards, cubic meters, and an optional material-cost estimate using your supplier’s price.

Quick answer: A 120 ft footing run × 24 in wide × 12 in thick contains 8.89 yd³ of concrete. With an example 10% allowance, the estimate is 9.78 yd³. These sample dimensions are not a footing design recommendation.

1. Choose what to include

Changing units converts the entered dimensions automatically.

Enter the total run after resolving corner and intersection overlaps. Use dimensions from your plan.

Solid poured concrete only. Measure wall height above the footing; this estimates gross volume before openings.

Enter the slab area only. Exclude portions already counted in another component.

10% is an example. Adjust it to suit the pour.

Optional supplier price

Material only. Delivery, tax, short-load fees, pumping, and labor may be separate.

Enable JavaScript to use this calculator.

2. Your concrete takeoff

—

Cubic yards including allowance

Your estimate will appear here.

Select the components included in your pour.

Quantity estimate based on entered geometry. Footing dimensions, wall sizes, soil bearing, frost protection, reinforcement, and concrete strength must come from the project design.

What this foundation calculator measures

A foundation is not usually one solid block the size of the building footprint. This tool adds the concrete volumes of the components you select, then applies your allowance once to the combined total.

  • Continuous footing: total footing run × footing width × footing thickness.
  • Poured stem wall: wall run × wall thickness × wall height above the footing.
  • Separate slab: slab length × slab width × slab thickness.

The wall result is a gross solid-concrete volume before openings. A hollow CMU foundation wall needs a separate block and grout takeoff. Excavation, gravel, reinforcement, and installed construction cost are separate quantities.

How to enter foundation measurements

  1. Use the dimensions from your drawings. The default values demonstrate the calculation; they do not select an appropriate footing or slab size.
  2. Measure the actual footing run. For a closed rectangular strip with uniform width, its centerline perimeter can be used. Outside-edge perimeter and centerline perimeter are different.
  3. Resolve intersections. For internal branches or irregular foundations, break the plan into volumes that do not overlap. Adding every full-length run can count intersection concrete twice.
  4. Keep the components separate. Enter stem-wall height above the footing. For a monolithic thickened edge, count only the additional edge volume below the slab, so slab concrete is not added twice.
  5. Review each pour separately. If footing, wall, and slab will be delivered on different days, calculate them separately as well. Each delivery may have its own order increments and charges.

Worked example: footing, wall, and slab

The example below adds independent, non-overlapping takeoff quantities. The slab dimensions are its clear measured area, not the outside foundation footprint. All sizes are illustrative.

Component concrete takeoff before allowance
Component Entered dimensions Base volume
Footing 120 ft × 24 in × 12 in 240.00 ft³ / 8.89 yd³
Poured stem wall 120 ft × 8 in × 2 ft 160.00 ft³ / 5.93 yd³
Separate slab 38 ft × 18 ft × 4 in 228.00 ft³ / 8.44 yd³
Total before allowance Sum of components 628.00 ft³ / 23.26 yd³
With 10% extra Base total × 1.10 690.80 ft³ / 25.59 yd³

If a supplier quoted $150 per cubic yard, the example material estimate would be 25.58519 × $150 = $3,837.78. This is an arithmetic example, not a current market price or a complete foundation bid.

Foundation concrete formulas

Component volume (ft³) = length (ft) × width or thickness (ft) × depth or height (ft)

Base total (yd³) = sum of selected component volumes (ft³) ÷ 27

Total with allowance = base total × (1 + extra percentage ÷ 100)

Material cost = allowance-adjusted volume × supplier price in the matching volume unit

Convert inches to feet by dividing by 12. In metric mode, convert millimeters to meters by dividing by 1,000. One cubic yard equals 27 cubic feet; one cubic foot equals 0.028316846592 cubic meters. The tool keeps unrounded values for its calculations.

Footing quantity reference

Each row shows 10 linear feet of continuous footing before allowance. These are quantity examples, not approved footing sizes.

Width × thickness Base volume per 10 ft Cubic yards
16 in × 8 in 8.89 ft³ 0.329 yd³
20 in × 10 in 13.89 ft³ 0.514 yd³
24 in × 12 in 20.00 ft³ 0.741 yd³
30 in × 12 in 25.00 ft³ 0.926 yd³

Before placing a concrete order

  • Confirm the formed or excavated geometry. Uneven trenches and over-excavation can increase actual placement volume.
  • Choose your allowance for the actual pour. Enter 0% for a net geometry takeoff. The example 10% is not a universal requirement.
  • Check the supplier’s order increments. Display rounding is not an automatic order-rounding rule.
  • Confirm the specified mix and placement arrangements. A quantity calculation does not determine strength, exposure requirements, reinforcement, access, pumping, or placement sequencing.
  • Obtain a complete quote. Material volume multiplied by a unit price excludes separate delivery, tax, pumping, labor, formwork, excavation, reinforcement, and other project costs.

Foundation calculator questions

How much concrete does a 40 × 20 foundation need?

The footprint alone is not enough. A solid slab needs its thickness; a footing needs its actual run, width, and thickness; a poured wall also needs wall height and thickness. Select and measure the components your foundation actually contains.

How do I find the footing perimeter?

For a closed rectangular footing with uniform width, use the centerline length and width: centerline perimeter = 2 × (length + width). A 40 ft × 20 ft centerline rectangle has a 120 ft run. For intersections, steps, or irregular sections, use a takeoff that resolves overlaps.

Can this choose footing width or foundation depth?

No. Enter sizes from the project design. Soil conditions, loads, frost protection, and applicable requirements affect foundation design and cannot be determined by a basic volume tool.

Does this work for a monolithic slab?

It can add rectangular volumes when they do not overlap. Enter the full slab once and count only thickened-edge concrete below that slab thickness. Sloped or haunched edges and complicated profiles need a separate geometric takeoff.

Can I calculate isolated pads or round piers?

This tool focuses on continuous footings, poured stem walls, and rectangular slabs. Use the Concrete Calculator linked below for a rectangular pad or round solid pier. Calculate separate geometries individually before combining them.

How do I handle hollow concrete block walls?

Do not treat a hollow CMU wall as solid poured concrete. Estimate blocks separately and use the specified grouting pattern and product cell-fill data for grout quantities.

Why does my supplier quote a different amount or cost?

Actual measurements, allowance, supplier order increments, minimum loads, separate pours, mix requirements, and delivery or pumping fees can change the order and quote. Compare the same scope and units.

Continue your material takeoff

Use the Concrete Calculator for individual slabs, rectangular pads, or round columns. For masonry foundation walls, use the CMU Block Calculator and Mortar Calculator. Use the Rebar Calculator to take off quantities from the reinforcement layout in your plans.